Latest News Current Position: Home > NEWS CENTER > Latest News

Commissioning of Brazil Candiota Coal-fired Power Plant Reaches Full Capacity

Post on: 2010-11-15

On Nov. 14, the power generation of coal-fired generating units of Brazil Candiota Coal-fired Power Plant reached the full capacity of 350MW at 17:28, after it started commissioning on Nov. 9 local time. All the parameters are normal at the full capacity and the vapor pressure & temperature are lower than specified indexes. The full-capacity commissioning of the project lays a solid foundation for the next 168-hour commissioning, acceptance and operation.